Great Glen Way Diversion – Coire Glas 2022

Trail

Construction phase

Following the successful planning application submitted by the company in 2021, the company was selected by SSE to undertake the construction phase. The construction included repairs and upgrading of 3km of exiting forest track plus 1500m of new path as per the planning application approved in December 2021.

Whilst the terrain for the new build section was challenging, this was further compounded by the Client request to construct the works in the early months of 2022. The construction duration was 16 weeks and was completed on time in April 2022.

The Client, following completion of the path diversion project produced the following short video.